| Daily Generation |
| Dhaka | ||||||||||
| Sl | Power Station Name |
Unit X Capacity (MW) |
Installed Capacity |
Derated Capacity |
Forecast on | Actual Generation of | Today's Proable | |||
|---|---|---|---|---|---|---|---|---|---|---|
| 14-04-2026 | 14-04-2026 | 15-04-2026 | ||||||||
| Day Peak | Eve Peak | Day Peak | Eve Peak | Day Peak | Eve Peak | |||||
| 1 | Ghorashal Repowered CCPP Unit 3 (GT) | 1x260 | 260 | 260 | 0 | 0 | 0 | 0 | 0 | 0 |
| 2 | Ghorasal Repowered CCPP UNIT-4 | 1*210 | 210 | 180 | 230 | 230 | 0 | 0 | 230 | 230 |
| 3 | b) Ghorasal TPP Unit 5 | 1x210 | 210 | 190 | 190 | 190 | 0 | 0 | 190 | 190 |
| 4 | Ghorashal 365 MW CCPP Unit -7 | 1x254+1x126 | 365 | 365 | 260 | 260 | 0 | 0 | 260 | 260 |
| 5 | Ghorashal 108 MW PP (Regent) | 34*3.35 | 108 | 108 | 98 | 98 | 0 | 0 | 98 | 98 |
| 6 | Tongi 80 MW GT PP | 1X105 | 105 | 105 | 0 | 0 | 0 | 0 | 0 | 0 |
| 7 | Horipur GT PP | 2*32 | 00.00 | 00.00 | 0 | 0 | 0 | 0 | 0 | 0 |
| 8 | Meghnaghat 450 MW CCPP (MPL) | 2x140+1x170 | 450 | 450 | 450 | 450 | 225 | 180 | 450 | 450 |
| 9 | 210 MW Shiddirganj TPP | 1X210 | 210 | 115 | 0 | 0 | 0 | 0 | 0 | 0 |
| 10 | Horipur 412 MW CCPP | 1x273+1x139 | 412 | 400 | 412 | 412 | 409 | 412 | 412 | 412 |
| 11 | Siddirganj 2*120 MW GTPP | 2X105 | 210 | 208 | 210 | 210 | 0 | 0 | 210 | 210 |
| 12 | Siddhirganj CCPP 335 MW | 1x217+1x118 | 335 | 335 | 335 | 335 | 300 | 300 | 335 | 335 |
| 13 | Meghnaghat 335 MWCCPP (Summit) | 2*110+1*110 | 335 | 335 | 335 | 335 | 0 | 0 | 335 | 335 |
| 14 | Madanganj-55 MW PP (Summit) | 5X17.08+1X11.3 | 55 | 55 | 55 | 55 | 55 | 55 | 55 | 55 |
| 15 | Gagnagar102 MW PP (Digital Power) | 12X8.924 | 102 | 102 | 0 | 0 | 0 | 0 | 0 | 0 |
| 16 | Narshingdi 22 MW PP(Doreen) | 08 | 00 | 00 | 0 | 0 | 0 | 0 | 0 | 0 |
| 17 | Summit Power ( Ashulia) | 00.00 | 45 | 45 | 33 | 33 | 26 | 22 | 33 | 33 |
| 18 | Summit Power Madhabdi | 6*3.67+7*8.73 | 35 | 35 | 22 | 22 | 14 | 21 | 22 | 22 |
| 19 | Maona 33 MW PP(Summit) | 4x8.73 | 00 | 00 | 0 | 0 | 0 | 0 | 0 | 0 |
| 20 | Rupganj 33 MW PP(Summit) | 4x8.73 | 00 | 00 | 0 | 0 | 0 | 0 | 0 | 0 |
| 21 | Gazipur 52 MW PP | 6x8.90 | 52 | 52 | 52 | 52 | 49 | 50 | 52 | 52 |
| 22 | Gazipur 100 MW PP | 6x18.415 | 105 | 105 | 105 | 105 | 105 | 105 | 105 | 105 |
| 23 | Kodda 150 MW Power Plant | 9x17.06 | 149 | 149 | 149 | 149 | 121 | 137 | 149 | 149 |
| 24 | Kamalaghat 54 MW PP (Banco Energy) | 3x18.69 | 54 | 54 | 54 | 54 | 17 | 0 | 54 | 54 |
| 25 | Kodda 300 MW PP Unit-2 (Summit) | 18x17.076 | 300 | 300 | 300 | 300 | 260 | 293 | 300 | 300 |
| 26 | Kodda 149 MW PP Unit-1(Summit) | 8x18.415+1x8.97 | 149 | 149 | 149 | 149 | 149 | 149 | 149 | 149 |
| 27 | Nababganj 55 MW PP (Southern) Power | 3x19.3 | 55 | 55 | 55 | 55 | 0 | 17 | 55 | 55 |
| 28 | Manikganj 55 MW PP (Northen) | 3x19.3 | 55 | 55 | 55 | 55 | 0 | 35 | 55 | 55 |
| 29 | Meghnaghat 104 MW PP (OPSL) | 6x18.5 | 104 | 104 | 104 | 104 | 0 | 0 | 104 | 104 |
| 30 | Manikgonj 162MW PP (MPGL) | 9x18 | 162 | 162 | 162 | 162 | 17 | 17 | 162 | 162 |
| 31 | Manikgonj 35 Mw Solar PP (Inspect) | 1x35 | 35 | 35 | 33 | 0 | 33 | 0 | 33 | 0 |
| 32 | Kanchan Purbachal Power Generation | 3x19.404 | 55 | 55 | 55 | 55 | 17 | 35 | 55 | 55 |
| 33 | Keraniganj 100 MW PP(Powerpac) 100 MW | 8X13.45 | 00 | 00 | 0 | 0 | 0 | 0 | 0 | 0 |
| 34 | Unique Meghnaghat 584MW CCPP | 00.00 | 584 | 584 | 584 | 584 | 400 | 460 | 584 | 584 |
| 35 | Meghnaghat 583 MW CCPP (Summit) | 00.00 | 583 | 583 | 583 | 583 | 0 | 0 | 583 | 583 |
| 36 | Meghnaghat (Jera) 718 MW CCPP | 00.00 | 718 | 718 | 718 | 718 | 0 | 0 | 718 | 718 |
| 37 | Sreepur150 MW | 150 | 160 | 160 | 160 | 160 | 142 | 142 | 160 | 160 |
| Total | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | ||
| Chittagong | ||||||||||
| Sl | Power Station Name |
Unit X Capacity (MW) |
Installed Capacity |
Derated Capacity |
Forecast on | Actual Generation of | Today's Proable | |||
|---|---|---|---|---|---|---|---|---|---|---|
| 14-04-2026 | 14-04-2026 | 15-04-2026 | ||||||||
| Day Peak | Eve Peak | Day Peak | Eve Peak | Day Peak | Eve Peak | |||||
| 1 | Karnaphuli Hydro PP Unit-1,2,3,4,5 | 2*40,3*50 | 230 | 230 | 80 | 80 | 70 | 70 | 80 | 80 |
| 2 | Chattogram Tpp | 1X210 | 420 | 360 | 0 | 0 | 0 | 0 | 0 | 0 |
| 3 | Kaptai 7 MW Solar PP | 00.00 | 6 | 6 | 4 | 0 | 3.99 | 0 | 4 | 0 |
| 4 | Raozan 25 MW PP | 3x8.9 | 25 | 25 | 26 | 26 | 25.5 | 17 | 26 | 26 |
| 5 | Teknaf 20 MW PP (Solartech) | 1x20 | 20 | 20 | 18 | 0 | 18 | 0 | 18 | 0 |
| 6 | Patenga 50 MW PP(Baraka) | 8X6.89 | 50 | 50 | 50 | 50 | 19 | 50 | 50 | 50 |
| 7 | Sikalbaha 105 MW PP( Baraka Sikalbaha) | 6x18.415 | 105 | 105 | 105 | 105 | 34 | 51 | 105 | 105 |
| 8 | b) Shikalbaha Peaking (GT) | 1x150 | 150 | 150 | 0 | 0 | 0 | 0 | 0 | 0 |
| 9 | Shikalbaha 225 MW CCPP | 1x150+1x75 | 225 | 225 | 215 | 220 | 215 | 217 | 215 | 220 |
| 10 | Anwara 300 MW PP (United) | 17x17.078+3x8.04 | 300 | 300 | 300 | 300 | 16 | 16 | 300 | 300 |
| 11 | Juldah 100 MW PP Unit-3(Acorn) | 8x13.45 | 100 | 100 | 100 | 100 | 12 | 12 | 100 | 100 |
| 12 | Dohazari Kalaish 100 MW PP | 6 X 17.0 | 102 | 98 | 68 | 68 | 0 | 67 | 68 | 68 |
| 13 | Hathazari 100 MW Peaking pp | 11x8.9 | 98 | 98 | 56 | 64 | 36 | 54 | 56 | 64 |
| 14 | Malancha, Ctg.EPZ (United) | 5*8.73+3*9.34 | 00 | 00 | 40 | 40 | 32 | 36 | 5 | 24 |
| 15 | Chittagong 108 MW PP ECPV | 16x7.00 | 108 | 108 | 108 | 108 | 33 | 38 | 108 | 108 |
| 16 | Sikalbaha 54 MW Power Plant (Jodiac Power) | 3x18.55+1x3.6 | 54 | 54 | 54 | 54 | 0 | 0 | 54 | 54 |
| 17 | Karnaphuli Power Ltd. | 6x18.41+1x6.4 | 110 | 110 | 110 | 110 | 56 | 54 | 110 | 110 |
| 18 | Juldah Unit-2 (Acorn) | 8x13.6 | 100 | 100 | 100 | 100 | 10 | 12 | 100 | 100 |
| 19 | Chattogram 116MW PP (Anlima Energy Ltd.) | 6x21.06 | 116 | 116 | 116 | 116 | 90 | 86 | 116 | 116 |
| 20 | Mirsharai 150MW | 9x18.5 | 163 | 160 | 163 | 163 | 17 | 163 | 163 | 163 |
| 21 | Chattogram 2*612MW Coal Based PP (SS Power Unit-1) | 00.00 | 1224 | 1224 | 1224 | 1224 | 301 | 551 | 1224 | 1224 |
| 22 | Matarbari 2*600MW (CPGCL) | 00.00 | 1150 | 1150 | 160 | 160 | 160 | 200 | 160 | 200 |
| 23 | Coxs |Bazar wind pp | 0.00 | 60 | 60 | 3 | 11 | 4 | 10 | 6 | 0 |
| Total | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | ||
| Comilla | ||||||||||
| Sl | Power Station Name |
Unit X Capacity (MW) |
Installed Capacity |
Derated Capacity |
Forecast on | Actual Generation of | Today's Proable | |||
|---|---|---|---|---|---|---|---|---|---|---|
| 14-04-2026 | 14-04-2026 | 15-04-2026 | ||||||||
| Day Peak | Eve Peak | Day Peak | Eve Peak | Day Peak | Eve Peak | |||||
| 1 | ASHUGONJ 50 MW | 14*3.968 | 53 | 47 | 42 | 42 | 39 | 42 | 42 | 42 |
| 2 | Ashuganj CCPP-225MW | 1X142+1*75 | 221 | 221 | 221 | 221 | 181 | 203 | 221 | 221 |
| 3 | Asuganj 450 MW CCPP South | 1x360 | 360 | 360 | 342.01 | 342.01 | 335 | 345 | 342.01 | 342.01 |
| 4 | Asugonj 450 MW CCPP NORTH | 1x361 | 360 | 360 | 240 | 240 | 0 | 0 | 240 | 240 |
| 5 | Ashuganj 420 MW CCPP(East) GT | 1x284 | 400 | 400 | 393 | 393 | 380 | 393 | 393 | 393 |
| 6 | Asuganj 195 MW PP (APACL united) | 20X9.73+1X16 | 195 | 195 | 195 | 195 | 172 | 81 | 195 | 195 |
| 7 | Ashuganj 51 MW PP (Midland) | 6X9.34 | 51 | 51 | 51 | 51 | 51 | 51 | 51 | 51 |
| 8 | Ashuganj 150 MW PP midland | 23X7.015 | 150 | 150 | 150 | 150 | 20 | 138 | 150 | 150 |
| 9 | Titas 50 MW PP (Dautkandi) | 6X8.92 | 52 | 52 | 32 | 32 | 20 | 36 | 32 | 32 |
| 10 | Chandpur 150 MW CCPPP | 1X106+1X57 | 163 | 163 | 163 | 163 | 0 | 0 | 163 | 163 |
| 11 | Chandpur 200 MW Desh Energy | 12X18.415 | 200 | 200 | 200 | 200 | 17 | 196 | 200 | 200 |
| 12 | Feni, 11 MW PP (Doreen) | 4X2.90 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| 13 | Jangalia 52 MW PP (Lakdamavi) | 6X8.92 | 52 | 52 | 52.2 | 52.2 | 0 | 0 | 52.2 | 52.2 |
| 14 | Comilla 25 MW PP Summit | 3*3.67+2*6.97 | 25 | 25 | 24.5 | 24.5 | 20 | 20 | 24.5 | 24.5 |
| 15 | Fani 114MW Power Plant(Lakdam) | 7*18.415+1.9.78 | 114 | 114 | 114 | 114 | 0 | 0 | 114 | 114 |
| 16 | Chowmuhani 113MW | 12.*9.78+2*3.1 | 113 | 113 | 113 | 113 | 9 | 9 | 113 | 113 |
| 17 | Chandpur 115MW PP (Dorren) | 4x18.516+2x25.428 | 115 | 115 | 115 | 115 | 0 | 34 | 115 | 115 |
| 18 | Ashuganj 55 MW (Precision) | 15*4 | 55 | 55 | 52.82 | 52.82 | 44 | 5 | 52.82 | 52.82 |
| 19 | Sonagazi 75MW Solar Power Plant | 00.00 | 75 | 75 | 70 | 0 | 46 | 0 | 70 | 0 |
| 20 | Import India(Tripura) | 1X100 | 160 | 160 | 84 | 78 | 176 | 178 | 84 | 76 |
| Total | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | ||
| Mymensingh | ||||||||||
| Sl | Power Station Name |
Unit X Capacity (MW) |
Installed Capacity |
Derated Capacity |
Forecast on | Actual Generation of | Today's Proable | |||
|---|---|---|---|---|---|---|---|---|---|---|
| 14-04-2026 | 14-04-2026 | 15-04-2026 | ||||||||
| Day Peak | Eve Peak | Day Peak | Eve Peak | Day Peak | Eve Peak | |||||
| 1 | RPCL, 210 MW CCPP, Mymensingh | 4X35+1X70 | 210 | 202 | 157.5 | 157.5 | 33 | 98 | 157.5 | 157.5 |
| 2 | Jamalpur 115 MW PP (United) | 12x9.87 | 115 | 115 | 70 | 70 | 78 | 69 | 10 | 10 |
| 3 | Mymenshingh 200 mwpp (United) | 21x9.780 | 200 | 200 | 10 | 10 | 31 | 48 | 60 | 60 |
| 4 | Sarishabari 3 MW Solar Plant | 1*3 | 3 | 3 | 2.1 | 0 | 1.75 | 0 | 2.3 | 0 |
| 5 | Sutiakhali 50 MW Solar PP | 50 MW | 50 | 50 | 48 | 0 | 43.49 | 0 | 46 | 0 |
| 6 | Bhairov 54MW PP | 1 | 54 | 54 | 54.5 | 54.5 | 0 | 17 | 54.5 | 54.5 |
| 7 | Tangail 22 MW PP )Palli Power Gen) | 4x6.7 | 22 | 22 | 22 | 22 | 0 | 12 | 22 | 22 |
| Total | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | ||
| Sylhet | ||||||||||
| Sl | Power Station Name |
Unit X Capacity (MW) |
Installed Capacity |
Derated Capacity |
Forecast on | Actual Generation of | Today's Proable | |||
|---|---|---|---|---|---|---|---|---|---|---|
| 14-04-2026 | 14-04-2026 | 15-04-2026 | ||||||||
| Day Peak | Eve Peak | Day Peak | Eve Peak | Day Peak | Eve Peak | |||||
| 1 | Fenchuganj CCPP-1 (Gas) | 2x32+1x33 | 97 | 70 | 42 | 42 | 42 | 42 | 42 | 42 |
| 2 | Fenchuganj CCPP-2(New) | 2*35+1*35 | 104 | 90 | 30 | 30 | 30 | 30 | 30 | 30 |
| 3 | Kushiara 163 MW Fenchugonj | 1x109+1x54 | 163 | 163 | 163 | 163 | 152 | 154 | 163 | 163 |
| 4 | Hobiganj 11 MW (Confidence-EP) | 4X2.90 | 00 | 00 | 0 | 0 | 0 | 0 | 0 | 0 |
| 5 | Shajibazar GT Unit-8, 9 | 2x35 | 70 | 66 | 30 | 30 | 30 | 30 | 30 | 30 |
| 6 | Shahjibazar 330 MW | 330 | 330 | 330 | 100 | 100 | 0 | 102 | 100 | 100 |
| 7 | Sylhet 225MW CCPP | 1x142+1x89 | 231 | 231 | 100 | 100 | 97 | 96 | 100 | 100 |
| 8 | Sylhet 20MW GT | 1 x 20 | 20 | 20 | 20 | 20 | 0 | 0 | 20 | 20 |
| 9 | Shahjahanulla 25mw | 3*9.34 | 25 | 25 | 25 | 25 | 17 | 17 | 25 | 25 |
| 10 | Bibiana 341 MW CCPP(Summit) | 1*222+1*119 | 341 | 341 | 341 | 341 | 310 | 310 | 341 | 341 |
| 11 | Bibiana-3 CCPP 400 MW | 00.00 | 400 | 400 | 350 | 385 | 349 | 325 | 350 | 350 |
| 12 | Bibiyana South 383MW CCPP | 1x383 | 383 | 383 | 0 | 0 | 0 | 0 | 0 | 0 |
| 13 | Shahjibazar 100 MW GTPP | 1x100.00 | 100 | 100 | 0 | 0 | 0 | 0 | 0 | 0 |
| 14 | Shajibazar 86 MW(Shajibazar ) | 32x2.90 | 86 | 86 | 83 | 83 | 78 | 81 | 86 | 86 |
| 15 | Moulvibazar 10 MW Solar Power Plant | 1*10 | 10 | 10 | 0 | 0 | 12 | 0 | 0 | 0 |
| Total | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | ||
| Khulna | ||||||||||
| Sl | Power Station Name |
Unit X Capacity (MW) |
Installed Capacity |
Derated Capacity |
Forecast on | Actual Generation of | Today's Proable | |||
|---|---|---|---|---|---|---|---|---|---|---|
| 14-04-2026 | 14-04-2026 | 15-04-2026 | ||||||||
| Day Peak | Eve Peak | Day Peak | Eve Peak | Day Peak | Eve Peak | |||||
| 1 | Bheramara GT (Unit-3) | 0 | 00 | 00 | 0 | 0 | 0 | 0 | 0 | 0 |
| 2 | Bherama 410 MW CCPP | 1x278+1X132 | 410 | 410 | 410 | 410 | 171 | 247 | 410 | 410 |
| 3 | Faridpur 50 MW Peaking PP | 8X6.89 | 54 | 54 | 27 | 27 | 0 | 20 | 27 | 27 |
| 4 | Gopalganj 100 MW Peaking PP | 16X6.98 | 109 | 109 | 50 | 50 | 0 | 43 | 50 | 50 |
| 5 | Khulna 225 MW CCPP | 1X150+1x75 | 230 | 230 | 230 | 230 | 0 | 0 | 230 | 230 |
| 6 | Rupsha 105 MW orion rupsha | 6X18.445 | 105 | 105 | 105 | 105 | 0 | 0 | 105 | 105 |
| 7 | Modhumati 100mw Power Plant | 6X18.415 | 105 | 105 | 105 | 105 | 0 | 0 | 105 | 105 |
| 8 | Mongla Orion 100 MW Solar PP | 00.00 | 100 | 100 | 100 | 0 | 25 | 0 | 85 | 0 |
| 9 | Maitree Super Thermal 1320 MW PP (Unit-1) | 1*617 | 1234 | 1234 | 617.1 | 617.1 | 617.1 | 602 | 617.1 | 617.1 |
| 10 | Khulna 330 MW CCPP (GT) | 00.00 | 336 | 336 | 336 | 336 | 0 | 0 | 336 | 336 |
| 11 | Rupsha 800 MW CCPP | 00 | 00 | 00 | 0 | 0 | 0 | 0 | 0 | 0 |
| 12 | Bheramara HVDC Interconnector | 00.00 | 1000 | 1000 | 1000 | 1000 | 909 | 908 | 1000 | 1000 |
| 13 | Nepal | 40 | 40 | 40 | 0 | 0 | 0 | 0 | 0 | 0 |
| Total | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | ||
| Barisal | ||||||||||
| Sl | Power Station Name |
Unit X Capacity (MW) |
Installed Capacity |
Derated Capacity |
Forecast on | Actual Generation of | Today's Proable | |||
|---|---|---|---|---|---|---|---|---|---|---|
| 14-04-2026 | 14-04-2026 | 15-04-2026 | ||||||||
| Day Peak | Eve Peak | Day Peak | Eve Peak | Day Peak | Eve Peak | |||||
| 1 | Barisal 110MWPP (Summit) | 7X17.076 | 110 | 110 | 110 | 110 | 99 | 96 | 110 | 110 |
| 2 | Bhola 33MW PP Venture | 1X34.50 | 00 | 00 | 0 | 0 | 0 | 0 | 0 | 0 |
| 3 | Bhola 225 MW CCPP | 2x63+1x68 | 194 | 194 | 130 | 130 | 130 | 130 | 130 | 130 |
| 4 | PAYRA 1320 MW TPP | 00.00 | 1244 | 1244 | 1244 | 1244 | 1210 | 1197 | 1244 | 1244 |
| 5 | Potuakhali 150MW PP (UPPL) | 8x18.415+1x9.78 | 150 | 150 | 150 | 150 | 17 | 17 | 150 | 150 |
| 6 | Barishal Electric 307 MW | 1*307 | 307 | 307 | 307 | 307 | 307 | 277 | 307 | 307 |
| 7 | Barisal 1 MW Solar PP | 1*1 | 1 | 1 | 1 | 0 | 0 | 0 | 1 | 0 |
| 8 | Bhola 220 MW CCPP (Nutan Biddut BD Ltd) | 2x75+1x70 | 220 | 220 | 220 | 220 | 220 | 220 | 220 | 220 |
| 9 | Patuakhali 1320 MW (RNPL) | 00.00 | 590 | 590 | 300 | 300 | 306 | 404 | 250 | 300 |
| Total | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | ||
| Rajshahi | ||||||||||
| Sl | Power Station Name |
Unit X Capacity (MW) |
Installed Capacity |
Derated Capacity |
Forecast on | Actual Generation of | Today's Proable | |||
|---|---|---|---|---|---|---|---|---|---|---|
| 14-04-2026 | 14-04-2026 | 15-04-2026 | ||||||||
| Day Peak | Eve Peak | Day Peak | Eve Peak | Day Peak | Eve Peak | |||||
| 1 | a)Baghabari 71 MWGTPP | 1X71 | 71 | 71 | 0 | 0 | 0 | 0 | 0 | 0 |
| 2 | a)Baghabari 100 MWGTPP | 1*100 | 100 | 100 | 0 | 0 | 0 | 0 | 0 | 0 |
| 3 | Baghabari 50 MWPP Peaking | 6X8.9 | 52 | 52 | 47 | 47 | 40 | 38 | 40 | 40 |
| 4 | Bera 70 MW Peaking | 9*8.29 | 71 | 71 | 32 | 32 | 0 | 0 | 32 | 32 |
| 5 | Chapainawabgonj 100 MW | 00.00 | 104 | 104 | 92 | 92 | 0 | 51 | 90 | 90 |
| 6 | Katakhali 50 MW (Peaking)PP | 6x8.7 | 50 | 50 | 32 | 32 | 14 | 30 | 32 | 32 |
| 7 | Santahar 50 MW PP Peaking | 50MW | 50 | 50 | 30 | 30 | 0 | 0 | 30 | 30 |
| 8 | Sirajganj 225 MW CCPP Unit-1 | 1x150+1x75 | 210 | 210 | 214 | 214 | 160 | 160 | 214 | 214 |
| 9 | Sirajganj , 225MW PP Unit-2 | 1*141 | 220 | 220 | 220 | 220 | 0 | 0 | 220 | 220 |
| 10 | Sirajganj , 225MW PP Unit-3 | 1*141+1*79 | 220 | 220 | 220 | 220 | 140 | 140 | 220 | 220 |
| 11 | Sirajgonj-400 MW CCPP Unit4 | 1*282+1*132 | 414 | 414 | 413.79 | 413.79 | 365 | 385 | 413.79 | 413.79 |
| 12 | Ullapara 11 MW PP (Summit) | 4X2.90 | 00 | 00 | 0 | 0 | 0 | 0 | 0 | 0 |
| 13 | Natore 52 MW PP (Rajlanka) | 6x8.92 | 52 | 52 | 52.2 | 52.2 | 0 | 0 | 52.2 | 52.2 |
| 14 | Bagura 113 MW PP (Confidence) Unit-1 | 6*18.55 | 113 | 113 | 113 | 113 | 0 | 35 | 113 | 113 |
| 15 | Bogra 113MW PP(Confedence)-2 | 113.00 | 113 | 113 | 113 | 113 | 1 | 50 | 113 | 113 |
| 16 | Amnura 50 MW PP | 7*7.79 | 00 | 00 | 0 | 0 | 0 | 0 | 0 | 0 |
| 17 | Sirajgonj 6.55 MW Solar Power Plant | 1x6 | 6 | 6 | 6 | 0 | 2.51 | 0 | 6 | 0 |
| 18 | Sirajganj 68 MW Solar Park | 68 | 68 | 68 | 61 | 0 | 43 | 0 | 61 | 0 |
| 19 | Pabna Solar IPP 100MW | 100 | 100 | 100 | 100 | 0 | 111 | 0 | 100 | 0 |
| 20 | Sirajgonj 2 MW Wind Power Plant | 2 | 2 | 2 | 0 | 0 | 0 | 0 | 0 | 0 |
| 21 | Pabna 64 MW Solar Plant | 00.00 | 65.00 | 65.00 | 62 | 0 | 60.49 | 0 | 62 | 0 |
| 22 | Adani Power Jharkhanda Ltd | 00.00 | 1496 | 1436 | 1436 | 1436 | 1510 | 1478 | 1436 | 1436 |
| Total | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | ||
| Rangpur | ||||||||||
| Sl | Power Station Name |
Unit X Capacity (MW) |
Installed Capacity |
Derated Capacity |
Forecast on | Actual Generation of | Today's Proable | |||
|---|---|---|---|---|---|---|---|---|---|---|
| 14-04-2026 | 14-04-2026 | 15-04-2026 | ||||||||
| Day Peak | Eve Peak | Day Peak | Eve Peak | Day Peak | Eve Peak | |||||
| 1 | Barupukuria TPP Unit-1 & 2 | 1 x 125 | 250 | 170 | 55 | 55 | 55 | 52 | 55 | 55 |
| 2 | Barapukuria 275 MW TPP Unit-3 | 1x274 | 274 | 274 | 0 | 0 | 0 | 0 | 0 | 0 |
| 3 | Rangpur 20 MW GTPP | 1X20 | 20 | 20 | 0 | 0 | 0 | 0 | 0 | 0 |
| 4 | Rangpur 113 MW PP(Confidence)Rangpur | 7*16x2*3 | 113 | 113 | 113 | 113 | 0 | 92 | 113 | 113 |
| 5 | Syedpur 20 MW GTPP | 1X20 | 20 | 20 | 14 | 14 | 0 | 0 | 14 | 14 |
| 6 | Majhipara Tetulia 8 Mw Solar pp (Sympa)) | 8MW | 8 | 8 | 6.2 | 0 | 7.1 | 0 | 6.8 | 0 |
| 7 | Thakurgaon 115 MW PP (Energypac) | 6*20 | 115 | 115 | 115 | 115 | 35 | 114 | 115 | 115 |
| 8 | Lalmonirhat 30 MW Solar (Intraco) | 1*30 | 30 | 30 | 30 | 0 | 30 | 0 | 30 | 0 |
| 9 | Teesta Solar Limited | 00.00 | 200 | 200 | 187.62 | 0 | 157 | 0 | 200 | 0 |
| 10 | Saidpur 150 MW Simple Cycle Power Plant | 1*150 | 162 | 162 | 0 | 0 | 0 | 0 | 0 | 0 |
| Total | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | ||
| Under Maintenance | ||||||||||
| Sl | Power Station Name |
Unit X Capacity (MW) |
Installed Capacity |
Derated Capacity |
Forecast on | Actual Generation of | Today's Proable | |||
|---|---|---|---|---|---|---|---|---|---|---|
| 14-04-2026 | 14-04-2026 | 15-04-2026 | ||||||||
| Day Peak | Eve Peak | Day Peak | Eve Peak | Day Peak | Eve Peak | |||||
| 1 | Ghorashal 78.5 MW PP (MAX) | 2X40 | 0.00 | 0.00 | 0 | 0 | 0 | 0 | 0 | 0 |
| 2 | Horippur 360 MW CCPP (HPL) | 1*235+1*125 | 00 | 00 | 0 | 0 | 0 | 0 | 0 | 0 |
| 3 | Pagla (DPA) | 100*0.5 | 00 | 00 | 0 | 0 | 0 | 0 | 0 | 0 |
| 4 | Keranigonj 300 MW PP (ARP) | 256x1.4 | 0.00 | 0.00 | 0 | 0 | 0 | 0 | 0 | 0 |
| 5 | Bramhangoan 100MW PP (Aggreko) | 00.00 | 0.00 | 0.00 | 0 | 0 | 0 | 0 | 0 | 0 |
| 6 | Aurahati 100 mw PP (Agreeko) | 23x0.85+91x959 | 0.00 | 0.00 | 0 | 0 | 0 | 0 | 0 | 0 |
| 7 | Bosila 108 Mw PP(CLC) | 12x8.775+1x3.5 | 00 | 00 | 0 | 0 | 0 | 0 | 0 | 0 |
| 8 | Meghnaghat 100 MW (IEL) | 1x100 | 00 | 00 | 0 | 0 | 0 | 0 | 0 | 0 |
| 9 | Katpotty 52 MW PP (Sinha) | 7X7.90 | 00 | 00 | 0 | 0 | 0 | 0 | 0 | 0 |
| 10 | Siddhirganj 100 PP (Dutch Bangla) | 12X8.9 | 00 | 00 | 0 | 0 | 0 | 0 | 0 | 0 |
| 11 | Meghnaghat (reliance) 718MW CCPP | 00 | 00 | 00 | 0 | 0 | 0 | 0 | 0 | 0 |
| 12 | Chattogram Tpp:Unit-2 | 1 x 210 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| 13 | Barabkunda 22 MW PP (Regent) | 8x2.90 | 0.00 | 0.00 | 0 | 0 | 0 | 0 | 0 | 0 |
| 14 | Juldah 100 MW Unit-1 (Acorn) | 8X13.45 | 00 | 00 | 0 | 0 | 0 | 0 | 0 | 0 |
| 15 | Ashuganj (Aggreko) | 96*1.10 | 0.00 | 0.00 | 0 | 0 | 0 | 0 | 0 | 0 |
| 16 | Ashuganj TPP Unit-3 | 1X150 | 0.00 | 0.00 | 0 | 0 | 0 | 0 | 0 | 0 |
| 17 | Ashugonj TPP Unit-4 | 1x150 | 0.00 | 0.00 | 0 | 0 | 0 | 0 | 0 | 0 |
| 18 | Ashugonj TPP Unit-5 | 1 x 150 | 0.00 | 0.00 | 0 | 0 | 0 | 0 | 0 | 0 |
| 19 | B.Baria 68 MW | 72*1.10 | 0.00 | 0.00 | 0 | 0 | 0 | 0 | 0 | 0 |
| 20 | Feni 22 MW (Doreen) | 8X2.90 | 0.00 | 0.00 | 0 | 0 | 0 | 0 | 0 | 0 |
| 21 | Jangalia 33 MW PP (Summit) | 4X8.73 | 00 | 00 | 0 | 0 | 0 | 0 | 0 | 0 |
| 22 | Tangail 22 MW pp (Doreen) | 8X2.90 | 0.00 | 0.00 | 0 | 0 | 0 | 0 | 0 | 0 |
| 23 | Jamalpur 95 MW PP(Powerpac) | 12*8.924 | 00 | 00 | 0 | 0 | 0 | 0 | 0 | 0 |
| 24 | Fenchuganj 51 MW (Barakatullah) | 19X2.90 | 00 | 00 | 0 | 0 | 0 | 0 | 0 | 0 |
| 25 | Fenchugonj 51 MW PP (Barkatullah) | 19*2.90 | 00 | 00 | 0 | 0 | 0 | 0 | 0 | 0 |
| 26 | Sylhet 10 MW (Desh) | 6X1.95 | 0.00 | 0.00 | 0 | 0 | 0 | 0 | 0 | 0 |
| 27 | Sylhet 50 MW EPL | 27x2.0 | 0.00 | 0.00 | 0 | 0 | 0 | 0 | 0 | 0 |
| 28 | Noapara 40 MWPP (KhanjahanAli) | 40.00 | 00 | 00 | 0 | 0 | 0 | 0 | 0 | 0 |
| 29 | Khulna 115 PP MW (KPCL-2) | 7X7 | 00 | 00 | 0 | 0 | 0 | 0 | 0 | 0 |
| 30 | Baghabari 200 MWPP Peaking (Paramount) | 00. | 0.00 | 0.00 | 0 | 0 | 0 | 0 | 0 | 00 |
| 31 | Bogra 22 MW PP GBB | 6X4.0 | 0.00 | 0.00 | 0 | 0 | 0 | 0 | 0 | 0 |
| 32 | Bogra 20 MW PP (Energyprima) | 00.00 | 0.00 | 0.00 | 0 | 0 | 0 | 0 | 0 | 0 |
| 33 | Barapukuria TPP Unit-2 | 1 x 125 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| Total | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | ||
| Total Daily Generation Entry | |||||||
|   | Installed Capacity | Derated Capacity | Actual Day Peak | Actual Eve Peak | Proable Day Peak | Proable Eve Peak | |
|---|---|---|---|---|---|---|---|
| Total All Zone Area Generation | 0 | 0 | 0 | 0 | 0 | 0 | |